Bally's Las Vegas

RLS-CMC, Inc. acted as Construction Manager and Owner’s Representative for the IDAS installation of the Bally’s guestrooms and suites tower. RLS-CMC, Inc. provided pre-construction, design, engineering, and management services to successfully complete the 2-tower installation of the hotel. The Bally’s North tower required asbestos abatement to be performed prior to the scheduled DAS install. The RLS-CMC team was able to complete the asbestos abatement and a 3-floor installation with a 9-day turnaround. This project required over 500 antennas and 31 remote units to provide coverage to the Bally’s towers. The Bally’s DAS system is connected to the newly constructed head end, located in the Paris Hotel & Casino employee parking garage.

Location

3645 S Las Vegas Blvd · Las Vegas, NV 89109